›› 2015, Vol. 36 ›› Issue (7): 1989-1994.doi: 10.16285/j.rsm.2015.07.021

• Geotechnical Engineering • Previous Articles     Next Articles

Minimum safety thickness of water and mud inrush induced by filled-type karst water bearing structures based on theory of slice method

LI Shu-cai1,LIN Peng1,XU Zhen-hao1, 2,LI Li-ping1, 3,GUO Ming1, SUN Chao-qun1,WANG Jing1,SONG Shu-guang1   

  1. 1. Research Center of Geotechnical and Structural Engineering, Shandong University, Jinan, Shandong 250061, China; 2. State Key Laboratory for Geomechanics and Deep Underground Engineering, China University of Mining & Technology, Xuzhou, Jiangsu 221116, China; 3. Key Laboratory of Harbor, Waterway and Sedimentation Engineering of Ministry of Communications, Nanjing Hydraulic Research Institute, Nanjing, Jiangsu 210098, China
  • Received:2014-03-31 Online:2015-07-11 Published:2018-06-13

Abstract: In this paper, we propose a simplified analytical method for computing the minimum safety thickness of water and mud inrush induced by filled-type karst water bearing structures. The theory of slice method widely used to analyze the slope stability is applied to investigate the stability of the karst filling material. A simplified computational model is established for the complex system which consists of tunnel, karst filling material and karst conduit. In this model, it assumes that the stress of filling material along the surface to reach the state of limit equilibrium and the failure of filling material along the sliding surface to obey Mohr-Coulomb failure criterion. An equation is derived by using the equilibrium of forces to calculate the minimum safety thickness of water and mud inrush induced by filled-type karst water bearing structures, in which it is used for the application of the practical engineering problems. The results calculated by the proposed method are in good agreement with numerical simulations. It indicates that this method is applicable for the determination of the minimum safe thickness of water and mud inrush, which also provides an efficient way to explore the mechanism of water and mud inrush in karst tunnels.

Key words: slice method, filled-type, karst, water bearing structures, water and mud inrush, minimum safety thickness

CLC Number: 

  • U 45
[1] LIU Zong-hui, LIU Mao-mao, ZHOU Dong, LAN Ri-yan, WU Heng, WANG Ye-tian, . Recognition method of typical anomalies in karst tunnel construction based on attribute analysis of ground penetrating radar [J]. Rock and Soil Mechanics, 2019, 40(8): 3282-3290.
[2] YUAN Wei, LIU Shang-ge, NIE Qing-ke, WANG Wei, . An approach for determining the critical thickness of the karst cave roof at the bottom of socketed pile based on punch failure mode [J]. Rock and Soil Mechanics, 2019, 40(7): 2789-2798.
[3] HUANG Sheng-gen, LIU Dong-jun, HU Yong-jian,. Simulation analysis and application study of electromagnetic wave computed tomography in detecting karst caves [J]. , 2018, 39(S1): 544-550.
[4] LI Shu-cai, PAN Dong-dong, XU Zhen-hao, LI Li-ping, LIN Peng,. A model test on catastrophic evolution process of water inrush of a concealed karst cave filled with confined water [J]. , 2018, 39(9): 3164-3173.
[5] YIN Jun-fan, LEI Yong, CHEN Qiu-nan, LIU Yi-xin, DENG Jia-zheng,. Upper bound analysis of the punching shear failure of cave roof in karst area [J]. , 2018, 39(8): 2837-2843.
[6] ZHAO Ming-hua, TANG Xian-li, XIAO Yao, YANG Chao-wei . Model tests on punching properties of karst cave roof under pile tip considering different thick-span ratios [J]. , 2018, 39(4): 1159-1167.
[7] LI Jian-peng, NIE Qing-ke, LIU Quan-sheng, YU Jun-chao,. Risk assessment method of karst ground collapse based on weight back analysis [J]. , 2018, 39(4): 1395-1400.
[8] LI Hao, BAI Hai-bo, WU Jian-jun, LI Zhi-yong, MENG Qing-bin, GUO Jun-qing, ZHU De-fu, XIAO Meng, . D-P stochastic damage constitutive model and its application in preventing water inrush of karst collapsed column [J]. Rock and Soil Mechanics, 2018, 39(12): 4577-4587.
[9] ZHAO Ming-hua, ZHU Zhi-ren, HUANG Ming-hua, YANG Chao-wei, XU Zhuo-jun. Study on thickness of safety for cave roofs suffered bending failure in karst areas [J]. , 2018, 39(11): 4201-4209.
[10] LI Jian-peng, NIE Qing-ke, LIU Quan-sheng, JIA Xiang-xin,. Logistic regression model for stability assessment of karst ground collapse of Tangshan city [J]. , 2017, 38(S2): 250-256.
[11] LI Hong-bo, JIA Feng, LI Jing, LI Shuo-biao,. Key technologies for design of subsea tunnel of Dalian metro line 5 [J]. , 2017, 38(S1): 395-401.
[12] YANG Zi-han, YANG Xiao-li, XU Jing-shu, LI Yong-xin, SUN Zhi-bin,. Two methods for rock wall thickness calculation in karst tunnels based on upper bound theorem [J]. , 2017, 38(3): 801-809.
[13] HUANG MING, FU Jun-jie, CHEN Fu-quan, JIANG Song. Damage characteristics of karst cave roof and its safety thickness calculation under the coupling effect of pile-tip load and seismic wave [J]. , 2017, 38(11): 3154-3162.
[14] LI Li-ping, LIU Shang, LI Shu-cai, SHI Shao-shuai, CHEN Di-yang, ZHOU Yi,LIN Peng, WANG Jian-hua, LIU Cong,. Development of testing system for coupled seepage and triaxial stress measurements and its application to permeability characteristic test on filling medium [J]. , 2017, 38(10): 3053-3061.
[15] ZHANG Zhen, CHEN Zhong-da, ZHU Yao-ting, HU Wen-hua, WU Fu-quan, LIU Chao-qun,. Effect of in-situ stress on stability of underlying karst cave [J]. , 2016, 37(S2): 715-723.
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed   
[1] LIU Yu-cheng,CAO Shu-gang,LIU Yan-bao. Discussion on some time functions for describing dynamic course of surface subsidence due to mining[J]. , 2010, 31(3): 925 -931 .
[2] LIU En-long. Breakage mechanics for geomaterials: Breakage mechanism of structural blocks and binary-medium model[J]. , 2010, 31(S1): 13 -22 .
[3] JIE Yu-xin, YANG Guang-hua. Modification of elastoplastic models based on generalized potential theory[J]. , 2010, 31(S2): 38 -42 .
[4] YANG Jian-min, ZHENG Gang. Classification of seepage failures and opinion to formula for check bursting instability in dewatering[J]. , 2009, 30(1): 261 -264 .
[5] ZHOU Hua,WANG Guo-jin1,,FU Shao-jun,ZOU Li-chun,CHEN Sheng-hong. Finite element analysis of foundation unloading and relaxation effects of Xiaowan Arch Dam[J]. , 2009, 30(4): 1175 -1180 .
[6] YE Fei, ZHU He-hua, HE Chuan. Back-filled grouts diffusion model and its pressure to segments of shield tunnel[J]. , 2009, 30(5): 1307 -1312 .
[7] CHEN Lin, ZHANG Yong-xing, RAN Ke-xin. A method for calculating active earth pressure considering shear stress[J]. , 2009, 30(S2): 219 -223 .
[8] LUO Qiang , WANG Zhong-tao , LUAN Mao-tian , YANG Yun-ming , CHEN Pei-zhen. Factors analysis of non-coaxial constitutive model’s application to numerical analysis of foundation bearing capacity[J]. , 2011, 32(S1): 732 -0737 .
[9] WANG Yun-Gang ,ZHANG Guang ,HU Qi. Study of force characteristics of battered pile foundation[J]. , 2011, 32(7): 2184 -2190 .
[10] GONG Wei-ming, HUANG Ting, DAI Guo-liang. Experimental study of key parameters of high piled foundation for offshore wind turbine[J]. , 2011, 32(S2): 115 -121 .