  • 1. College of Civil Engineering and Architecture, Guangxi University, Nanning, Guangxi 530004, China; 2. Guangxi Key Laboratory of Disaster Prevention and Structural Safety, Guangxi University, Nanning, Guangxi 530004, China; 3. China Shipbuilding NDRI Engineering Co., Ltd., Shanghai 200063, China; 4. Guangxi Key Laboratory of Geomechanics and Geotechnical Engineering, Guilin University of Technology, Guilin, Guangxi 541004, China

Received date: 2015-03-18

  Online published: 2018-06-14

Abstract

The redundancy theory is introduced into the double-row steel sheet piles cofferdam design. The preliminary framework of the definition and design of double-row steel sheet piles cofferdam supporting system redundancy are proposed. Taking the rod system redundancy analysis for example, alternate path method is adopted to quantitatively analyze for redundancy of the rod system. The results show that the redundancy parameters of lower rods are significantly lower than the upper rods; their failure can significantly reduce the stiffness, strength and stability of cofferdam supporting system; their failure even leads to the destruction of the whole cofferdam to collapse; it is consistent with the engineering practice. The above analysis verified the applicability and feasibility of the redundancy theory for double-row steel sheet piles cofferdam engineering.

Cite this article

JIANG Jie , GU Qian-yan , HU He , YU Mei-xin , MA Shao-kun , . Study of redundancy of double-row steel sheet piles cofferdam[J]. Rock and Soil Mechanics, 2015 , 36(S1) : 518 -522 . DOI: 10.16285/j.rsm.2015.S1.090

Outlines

/