Experimental analysis of delay effect of construction parameters of shield tunnel on soil displacement in soft soil area

Expand
  • 1. Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education, Tongji University, Shanghai 200092, China; 2. Department of Geotechnical Engineering, Tongji University, Shanghai 200092, China; 3. Shanghai Urban Construction Municipal Engineering (Group) Co., Ltd., Shanghai 200065, China

Received date: 2016-06-20

  Online published: 2018-06-05

Supported by

This work was supported by the National Program on Key Basic Research Project of China:Tunnel Engineering Safety on High Water Pressure in the Sea (973 Program) (2015CB057800).

Abstract

Due to excess pore pressure and other factors of deep soft soil, the effect of adjusting the shield parameters on the soil displacement tends to have a certain delay. The adjustment of construction parameter in current session influences more on the soil displacement in later session rather than current. Two same monitoring sections are set up to survey the soil displacement from the shield tunnel in Shanghai soft soil. The effect of each parameter adjustment to the displacement disturbance is analyzed by changing the key shield parameters in different stages during construction. Chamber pressure is adjusted before the shield cutter reaching the monitoring section. Advancing speed is adjusted while shield cutter crosses the monitoring section. Grouting quantity is adjusted when shield tail reaching the monitoring section. Through the monitoring data and the time-effect analysis of the correlation coefficient, it is found that the soil displacement is affected by the disturbances of the pre-adjusted soil pressure when the shield crosses the cross-section, and the soil displacement at the shield tail reflects the squeezing effect caused by advance rate, while the displacement of soil at the late consolidation stage shows the stabilizing effect caused by the increase of the grouting amount when the shield tail prolapse. Therefore, it is not only necessary to deal with the current soil deformation, but also to pay attention to the deformation and prediction of the soil after the adjustment of the parameters so as to avoid the occurrence of accidents due to the delay effect in soft soil.

Cite this article

LIU Shu-jia, BAI Ting-hui, LIAO Shao-ming, CHEN Li-sheng, . Experimental analysis of delay effect of construction parameters of shield tunnel on soil displacement in soft soil area[J]. Rock and Soil Mechanics, 2017 , 38(3) : 857 -865 . DOI: 10.16285/j.rsm.2017.03.031

Outlines

/