Rock and Soil Mechanics ›› 2022, Vol. 43 ›› Issue (7): 1933-1941.doi: 10.16285/j.rsm.2021.1634

• Geotechnical Engineering • Previous Articles     Next Articles

Surface displacement during pipe roof construction of pipe-jacking group with large section

TANG Zheng1, WANG Hong-xin2, SUN De-an1, ZHANG Xiao2   

  1. 1. School of Mechanics and Engineering Science, Shanghai University, Shanghai 200444, China; 2. Shanghai Urban Construction Municipal Engineering (Group) Co. Ltd., Shanghai 200065, China
  • Received:2021-09-24 Revised:2022-04-27 Online:2022-07-26 Published:2022-08-04

Abstract: To study the law of surface displacement during pipe roof construction of pipe-jacking group, this paper analyses surface displacement data based on the Tianlin Road passing under Middle Ring Road Tunnel Project in Shanghai. Measured data shows that deformation development during the pipe roof construction can be divided into seven stages: 4 construction stages and 3 suspending construction stages. The surface displacement during the pipe roof construction comprises ground loss settlement and ground heave caused by grouting. In the suspension stages, the surface displacement is consolidation settlement. In this paper, the surface displacement is described by the Peck equation. The width coefficient i of surface settlement trough and the ground loss ratio η were back analyzed from the field measured data. Based on the analysis results, the calculation formulas of i and η were proposed for Shanghai soft clay. i is related with the pipe radius R, pipe buried depth h and internal friction angle of soil φ, and the formula of η is described by a hyperbolic function of time after jacking. The surface heave caused by the grouting can be separated to the negative ground loss caused by each pipe jacking with grouting. The above method was used to predict the surface displacement and the predicted results were compared with measured data to verify the correctness of the method in this paper, which can provide scientific reference for the prediction of surface displacement caused by similar pipe roof method construction.  

Key words: pipe roof method, pipe-Jacking group, surface displacement, grouting heave, Peck equation

CLC Number: 

  • TU 354
[1] XIE Ji-ren, QIAO Shi-fan, YU Peng-kun, UCHIMURA Taro, WANG Gong-hui, JIANG Yao, FANG Zheng, TIAN Jing-li. Surface tilt deformation of soil landslides based on laboratory and field tests [J]. Rock and Soil Mechanics, 2021, 42(3): 681-690.
[2] QI Hui, DING Xiao-hao, ZHANG Yang. Study of scattering of SH-waves by a buried elliptic inclusion near a vertical interface and ground surface vibration [J]. , 2016, 37(8): 2151-2158.
[3] MA Jun-wei,HU Xin-li,TANG Hui-ming,YONG Rui,XIA Hao. Surface displacement field measurement for landslide model test based on computer aided inspection [J]. , 2013, 34(S2): 477-485.
[4] LIN Cun-gang, WU Shi-ming, ZHANG Zhong-miao ,LIU Jun-wei,LI Zong-liang . Influences of shield advance rate and abnormal machine halt on tunnelling-induced ground surface settlements [J]. , 2012, 33(8): 2472-2482.
[5] ZHANG Yong-hui,LI Hong-xu,SHENG Qian,WU Kai,LI Zhi-yong,YUE Zhi-ping. Study of highway landslide monitoring and early warning based on surface displacements [J]. , 2010, 31(11): 3671-3677.
[6] ZHAO Jia-xi, QI Hui, YANG Zai-lin. Scattering of SH-waves by a shallow buried cylindrical inclusion with a partially debonded curve in half space [J]. , 2009, 30(5): 1297-1302.
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed   
No Suggested Reading articles found!