›› 2012, Vol. 33 ›› Issue (6): 1742-1746.

• Geotechnical Engineering • Previous Articles     Next Articles

Study of millisecond blasting technology of shaft Excavation by one-step deep-hole blasting

LI Ting-chun,LIU Hong-qiang,WANG Chao   

  1. Shandong Provincial Key Laboratory of Civil Engineering Disaster Prevention and Mitigation, Shandong University of Science and Technology, Qingdao, Shandong 266590, China
  • Received:2012-01-12 Online:2012-06-11 Published:2012-06-14

Abstract: The detonating delay time of millisecond blasting is an important parameter during shaft excavation by one-step deep-hole blasting. If detonating delay time and detonating sequences are reasonable, the millisecond blasting technology has many advantages. The foregoing blasting can create free face and compensating space for the following blasting to achieve the purpose of layered and segmented blasting. Also, the vibration damage of the surrounding rock can be reduced by decreasing detonated explosive charges in every turn. Based on deep-hole millisecond blasting theory, calculation methods of the detonating delay time of presplitting blasting, cut blasting, the same segmentation auxiliary holes blasting and the adjacent segmentation auxiliary holes blasting of shaft excavation by one-step deep-hole blasting are studied. In addition, six kinds of detonating sequences are put forward, such as bottom-up presplitting blasting, up and down before the middle smooth blasting, etc. The one-step deep-hole blasting technique is seen to meet the requirements in the Huaheng coal mine which proves that this research is applicable to other similar projects.

Key words: shaft excavation by one-step, millisecond blasting, detonating delay time, detonating sequences

CLC Number: 

  • TD 265
[1] ZHANG Zhi-chao ,CHEN Yu-min ,LIU Han-long . Numerical analysis and evaluation of simulation of nature earthquake by millisecond blasting technique [J]. , 2013, 34(1): 265-274.
[2] LING Tong-hua , LI Xi-bing , WANG Gui-yao . A study on initiative control of blast vibration damages [J]. , 2007, 28(7): 1439-1442.
[3] ZHANG Xian-tang , GAO Wen-le , ZHANG Jin-quan , ZHOU Hong-min,. Research on blasting excavation techniques for rock ditching of natural gas ducts [J]. , 2006, 27(S1): 1045-1049.
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed   
[1] . Numerical implementation of discontinuities in dual media 3D model for thermo-hydro-mechanical coupling[J]. , 2010, 31(2): 638 -644 .
[2] SUN De-an,CHEN Bo. Mechanical behavior of remolded overconsolidated Shanghai soft clay and its elastoplastic simulation[J]. , 2010, 31(6): 1739 -1743 .
[3] WANG Yang, TANG Xiong-jun, TAN Xian-kun, WANG Yuan-han. Mechanism analysis of floor heave in Yunling Tunnel[J]. , 2010, 31(8): 2530 -2534 .
[4] LEI Jin-bo,CHEN Cong-xin. Research on load transfer mechanism of composite foundation of rigid pile with cap based on hyperbolic model[J]. , 2010, 31(11): 3385 -3391 .
[5] WANG Deng-ke,LIU Jian,YIN Guang-zhi,WEI Li-de. Research on influencing factors of permeability change for outburst-prone coal[J]. , 2010, 31(11): 3469 -3474 .
[6] DING Guang-ya, CAI Yuan-qiang, XU Chang-jie. Analysis of vibration isolation of a row of rigid piles to plane SV waves in saturated soil[J]. , 2009, 30(3): 849 -854 .
[7] ZHANG Cheng-ping,ZHANG Ding-li,LUO Jian-jun,WANG Meng-shu,WU Jie-pu. Remote monitoring system applied to the construction of metro station undercrossing existing metro tunnel[J]. , 2009, 30(6): 1861 -1866 .
[8] WANG Jun, CAO Ping, LI Jiang-teng, LIU Ye-ke. Analysis of stability of tunnel-slope with rheological medium under rainfall infiltration[J]. , 2009, 30(7): 2158 -2162 .
[9] ZHANG Yuan, WAN Zhi-jun, KANG Jian-rong, ZHAO Yang-sheng. Analysis of stage characteristics of sandstone permeability under conditions of temperature and triaxial stress[J]. , 2011, 32(3): 677 -683 .
[10] TANG Shi-bin, TANG Chun-an, LI Lian-chong, ZHANG Yong-bin. Investigation on time-dependent deformation of tunnel induced by humidity diffusion[J]. , 2011, 32(S1): 697 -0703 .