Optimal analysis of construction schemes of small space tunnel with bidirectional eight traffic lanes in jointed rock mass

JIANG Kun1, 2, XIA Cai-chu1, BIAN Yue-wei1   

  1. 1. Key Laboratory of Geotechnical and Underground Engineering of Ministry of Education, Department of Geotechnical Engineering, Tongji University, Shanghai 200092, China; 2. Dalian Municipal Design and Research Institute Co., Ltd., Dalian, Liaoning 116001, China
  • Received:2010-10-26 Online:2012-03-10 Published:2012-03-12

Abstract: According to the construction conditions of Kuiqi No.2 small-space tunnel with super-large cross-section and eight traffic lanes in the second phase project of Fuzhou International Airport Highway, a discrete element analysis program is established to simulate the construction process. In the program, the double-heading construction method, CRD method and CD method have been simulated. The settlements of vault, horizontal deformations of middle rock pillar, horizontal deformations of surrounding rock and plastic zone of surrounding rock are analyzed and the advantages of the three methods are compared. Considering the characteristics of Kuiqi No.2 Tunnel, the practical construction scheme is optimized. The double-heading method is changed to CRD method at the tunnel entrance. The modification of construction method has great contribution to cut down the cost and to reduce erection time. The results provide some reasonable references to design and construction for similar engineering.

Key words: joined rock mass, small space tunnel, super-large cross-section, construction scheme, optimization analysis

CLC Number: 

  • U 455
[1] LIU Quan-sheng, PENG Xing-xin, LEI Guang-feng, WANG Jun-tao,. Geomechanical model test on excavation technology of supper-large cross-section ultra-shallow tunnel with cross rock pillar method [J]. , 2017, 38(10): 2780-2788.
[2] LIANG Fa-yun, CHEN Hai-bing. Optimization analysis of group piles below rigid raft with a cut-off method [J]. , 2011, 32(S1): 61-65.
[3] JI Mao-wei , WU Shun-chuan , GAO Yong-tao , GE Lin-lin , LI Xiao-jing . Construction monitoring and numerical simulation of multi-arch tunnel [J]. , 2011, 32(12): 3787-3795.
[4] LEI Yong-sheng. Research on protective measures of City Wall and Bell Tower due to underneath crossing Xi’an Metro Line No.2 [J]. , 2010, 31(1): 223-228.
[5] GONG Jian-wu, XIA Cai-chu, ZHU He-hua, TANG Ying. Optimal analysis of construction schemes for Heshang small-space tunnels with large section [J]. , 2009, 30(1): 236-240.
[6] LI Wen-jiang ,ZHU Yong-quan ,LIU Zhi-chun,. Research on mechanical behaviour and construction schemes of rock tunnel adjacent to existing road tunnel [J]. , 2006, 27(S1): 377-380.
[7] SHI Zong-feng. Design of construction scheme for Longtan special long tunnel [J]. , 2005, 26(S1): 321-324.
[8] WANG Ke-li. Construction scheme of tunnel passing through landslide area and fault zone [J]. , 2004, 25(4): 651-653.
[9] GU Zhi-meng, CHEN Jian. Structural optimizafion analysis of hydro-photoelectric pressure gauge and its experimental research [J]. , 2003, 24(2): 311-315.
Viewed
Full text


Abstract

Cited

  Shared   
  Discussed   
[1] QI Le,SHI Jian-yong,CAO Quan. Method for calculating rational thickness of cushion in rigid pile composite ground[J]. , 2009, 30(11): 3423 -3428 .
[2] YU Li-yuan,LI Shu-cai,XU Bang-shu. Stability analysis of Zhoushan subsea tunnel with drill-and-blast construction method[J]. , 2009, 30(11): 3453 -3459 .
[3] YANG Hui, CAO Ping, JIANG Xue-liang. Micromechanical model for equivalent crack propagation under chemical corrosion of water-rock interaction[J]. , 2010, 31(7): 2104 -2110 .
[4] ZHANG Peng, CHEN Jian-ping, QIU Dao-hong. Evaluation of tunnel surrounding rock quality with extenics based on rough set[J]. , 2009, 30(1): 246 -250 .
[5] LI Xiang,JIA Ming-tao,WANG Li-guan,BAI Yun-fei. Study of orefragment size prediction in block caving based on Monte Carlo stochastic simulation[J]. , 2009, 30(4): 1186 -1190 .
[6] YIN Sheng-bin, DING Hong-yan. Time series-projection pursuit regression model for predicting surface settlement during pit excavation[J]. , 2011, 32(2): 369 -374 .
[7] JIANG Xin-liang,LI Lin,YUAN Jie,YIN Jia-shun. Dynamic analysis of strata horizontal displacements induced by shield construction of deep tunnel[J]. , 2011, 32(4): 1186 -1192 .
[8] JI You-jun ,LIU Jian-jun ,CHENG Lin-song. Numerical simulation of tunnel excavation considering fluid solid coupling[J]. , 2011, 32(4): 1229 -1233 .
[9] XU Wen-Jie. Study of spatial effect and stability of large scale soil-rock mixture landslide[J]. , 2009, 30(S2): 328 -333 .